What’s Going On in the Process?
June 2009
Stakeholder Interviews
Department Interviews
Plan Ascension website creation
July 2009
Background and baseline analyses
Stakeholder Interviews
August 2009
Stakeholder Interviews
Background and Baseline Analyses
Community Meetings #1
Synthesis of Comm Mtg Results
September 2009
Creation of future growth scenarios
Analysis of future growth scenarios
Transportation mobility analysis
October 2009
Community Meetings #2
Community survey for alternative future growth scenarios
November 2009
Development of preferred future growth scenario
Draft outline of comprehensive plan
Analysis of preferred future growth scenario
January 2010
Community Meetings #3
February 2010
Plan Outline
March 2010
Draft Comprehensive Plan
April 2010
Review of draft plan
May 2010
Planning Commission / Public Hearing of the Plan
Plan Adoption
Comprehensive Plan Production
Public Meeting Schedule