What’s Going On in the Process?

June 2009

Stakeholder Interviews

Department Interviews

Plan Ascension website creation

July 2009

Background and baseline analyses

Stakeholder Interviews

August 2009

Stakeholder Interviews

Background and Baseline Analyses

Community Meetings #1

Synthesis of Comm Mtg Results

September 2009

Creation of future growth scenarios

Analysis of future growth scenarios

Transportation mobility analysis

October 2009

Community Meetings #2

Community survey for alternative future growth scenarios

November 2009

Development of preferred future growth scenario

Draft outline of comprehensive plan

Analysis of preferred future growth scenario

January 2010

Community Meetings #3

February 2010

Plan Outline

March 2010

Draft Comprehensive Plan

April 2010

Review of draft plan

May 2010

Planning Commission / Public Hearing of the Plan


Plan Adoption


Comprehensive Plan Production

Public Meeting Schedule

Printable Schedule and Flyer